This homeowner came to me for help redesigning the remaining dated areas of her house, including the bathrooms. She had been updating the home a little at a time and wanted those spaces to feel cohesive with the rooms she had already renovated. Her primary bathroom had barely changed since the house was built in the mid-1990s, and she was ready for something warm, moody and dramatic.
When she saw a walnut vignette in my showroom, we had our starting point. From there, we built the design around the pieces that still worked, including her existing bisque tub and shower surround.
The layout stayed the same, with a new walnut vanity, charcoal walls and lighter surfaces to balance them. We kept the tub and mirror and chose where spending more would make the biggest difference to her. Construction was fully completed in four weeks.
The project at a glance
Home: Massachusetts house built in the mid-1990s
Bathroom: Approximately 60 square feet
Scope: Updated finishes and fixtures while retaining the layout, tub, surround and mirror
Estimated cost: Approximately $27,500, excluding design fees
Planning and ordering: About four weeks of design, partly overlapping a 10-week vanity lead time and contractor selection
Construction: Four weeks, fully completed
Cost note: The contractor priced this bathroom and a separate powder room together. The primary bathroom total includes my estimated share of that contract, based on the relative size and scope of the rooms. The calculation appears below.
What she wanted to change
The layout was not the problem. She liked the vanity configuration, and the existing tub worked for the household. What bothered her was the appearance. She had already remodeled the kitchen and made other updates, and wanted the bathrooms to feel cohesive with the rest of the house.
She also had one very practical request: a handshower to make cleaning easier. A combination showerhead and handshower gave her that improvement without requiring additional holes in the existing tub and shower unit.
We replaced the vanity, countertop, sink, faucet, toilet, floor tile, vanity light and fan/light combination, updated the tub and shower fittings, and added accessories and an open shelf. The shower valve was replaced through a carefully cut opening in the wall, which was then patched.
You could call this a cosmetic bathroom remodel because the focus was updating the existing room. But it was still a substantial renovation involving demolition, plumbing, tile installation and several trades. Keeping the layout helped contain the scope.
How the warm and moody palette came together
Once she chose walnut, we selected Benjamin Moore Kendall Charcoal for the walls. The other finishes developed around those two choices.
The existing bisque tub and surround suited the warm palette. Rather than treating their color as something to hide, we worked with it. That is worth considering when you are updating a room: an older fixture can belong in a new design if the surrounding materials make sense with it.
The lighter floor and creamy Cambria Notting Hill countertop balanced the dark walls. She loved the bronze, black and gold details in the quartz. They connected with the wood and darker finishes without making the countertop feel over the top.
Keeping the vanity configuration
The Showplace vanity is walnut with Sparrow stain and measures 60 inches wide, 21 inches deep and 32.5 inches high, matching the size and configuration she already liked. She considered a taller vanity, but that would have meant changes to the existing outlets. After discussing the extra work, she decided she was happy with the original height.
The vanity and matching shelf cost $3,862 against a $3,000 allowance. Walnut carried an upcharge, and the shelf was included in that final cabinetry price. She loved the wood enough to make that a priority.
Mixing black with warm metal finishes
The Kohler Tone plumbing fixtures were matte black. Top Knobs Tuscany hardware in Tuscan Bronze brought a warmer finish to the walnut cabinetry. The light combined black with brass accents, and the brass door hardware and hinges related to those accents.
The finishes did not all match, but each had a connection to something else in the room. That was the goal when we discussed mixing metals.
A shelf instead of a cabinet above the toilet
She wanted something above the toilet without the weight of a wall cabinet. A basket sitting on the tank could interfere with opening the toilet lid, so a shelf provided a better spot for towels, toilet paper, a plant or artwork.
We ordered the walnut shelf with the vanity so the wood matched, then paired it with cast iron brackets.
Why the existing tub stayed
We considered a tub-to-shower conversion. I explained that the drain work could expand the project because we did not know exactly where the drain stack was. The general contractor confirmed that this conversion would require a larger drain line and access to complete that work.
Below the bathroom was her recently remodeled kitchen. Opening that ceiling and taking on the plumbing and shower work were more than she wanted to do. The tub worked for the household and suited the design, so she decided the conversion was not worth the added disruption and expense.
Before deciding on a conversion in your own home, find out what the work would involve, including access from below. Can You Convert a Bathtub to a Shower? Explained explains more of those considerations.
Where she held the scope and where she spent more
Keep the tub and surround: They worked, suited the warm palette and avoided expanding the plumbing scope
Keep the vanity size and height: She liked the configuration and accepted the existing height
Keep the mirror: It was still in good condition, and she preferred to avoid removal and possible wall repairs
Choose walnut cabinetry: The walnut was the starting point for the room
Upgrade the countertop: She loved the material and waited until after rough-ins to commit
Keeping those existing features limited the work. We did not obtain a separate price for every alternative, so there is no exact savings figure attached to those decisions.
What the bathroom remodel cost
The two selections that exceeded their allowances were the cabinetry and countertop. Here are their full costs, before looking at the overall estimate.
Vanity and matching shelf: Originally allowed $3,000; final cost $3,862.
Countertop and sink: Originally allowed $1,041; final cost $3,400.
The countertop allowance was for a stock stone or remnant and sink. The fabricator did not carry her chosen quartz, so bringing in the slab required a minimum square-footage purchase. That increased the cost by $2,359.
She waited until demolition and rough-ins were complete before committing to it. We had a second option ready if unexpected work used up the available money. When no surprises emerged at that stage, she went ahead with the quartz she loved.
If you are considering a similar upgrade, ask your contractor what risks and expenses remain before using your reserve. How Much Contingency Should You Budget for a Renovation? Explained. explains how to plan that money.
How the total was calculated
The general contractor’s $36,700 contract covered this bathroom and a separate powder room. I estimated the primary bathroom’s share at 65 percent based on the size and scope of each room. That is an allocation, not a separately invoiced final cost.
The contract already included the vanity and countertop allowances, along with selected materials such as the floor tile and shower fixtures. The breakdown below therefore adds only the allowance overages and separate purchases.
Estimated primary bathroom share of contractor contract: $23,855 Vanity and shelf overage: $862 Countertop and sink overage: $2,359 Shelf brackets: $76 Vanity hardware: $150 Light fixture: $120 Bathroom accessories: $67
Estimated total: $27,489
Rounded estimate: approximately $27,500, including sales tax, shipping and delivery. Design fees and additional chandelier work elsewhere in the house are excluded.
The homeowner bought the light and accessories separately, but their installation was included in the contractor’s price. Check that distinction when reviewing your own quote: a contractor may include installation while leaving the material purchase to you.
These are costs for one Massachusetts project completed in 2025. For broader planning guidance, see How Much Does a Bathroom Remodel Cost? Explained.
Why keeping the layout still involved several trades
The homeowner initially had questions about the difference between the material costs and the contractor’s price for both bathrooms. We went through the scope together: plumbing, electrical work, tile, painting and carpentry, plus permits, scheduling, management and business costs such as insurance.
She chose the convenience of having one contractor coordinate the work. Retaining the layout reduced what we were changing, but several trades still had to work in sequence.
The planning time and four weeks of construction
Design took about four weeks. She brought samples home, discussed them with her husband and took time to feel comfortable with the choices. I ordered the vanity during that process to keep things moving.
The vanity had a 10-week lead time. Three weeks of design overlapped that wait, while contractor vetting, homeowner decisions and remaining selections continued. The contractor scheduled construction around the vanity’s expected arrival.
Once construction started, the bathroom was fully completed in four weeks. They lived at home throughout the project and had another full bathroom available. If this will be your only full bathroom, plan for that downtime before work begins. See How Long Does a Bathroom Remodel Take? Explained for more about the stages.
The tub spout issue the team caught early
At plumbing rough-in, the plumber noticed an unusually large opening behind the old tub spout. My design board was included with the plans, and he saw that the slimmer replacement might not cover it.
He flagged it, the general contractor called me, and I found a different spout with a large enough footprint. It was in stock and did not delay completion.
That is one reason I include selections with the drawings. The plumber could compare the planned fixture with what was actually there and catch the conflict before the finishing stage.
The mirror was another deliberate choice
I would have preferred to replace the large unframed mirror during the renovation. She wanted to keep it because it was in good condition. We discussed the possibility of wall repairs if it was glued in place, and the need to protect the new countertop if it ever had to be removed later. She understood the tradeoff and chose to keep it.
What to take from this bathroom transformation
The walnut and countertop were worth spending more on to her. A different layout, a new shower and a taller vanity were not. Those decisions let us create the warm, dramatic bathroom she wanted within a scope she was comfortable taking on.
Before deciding how much of your own bathroom to replace, separate what bothers you about its appearance from what does not work. What would moving a fixture actually improve? Could an existing tub or mirror belong in the new design? Which selections matter enough to you to spend more on?
Start with the Bathroom Needs vs Wants Checklist, then use the free Plan Like a Pro: Bathroom Renovation Quick-Start Guide to work through the decisions before construction begins.
Products and Finishes Used
Vanity and matching shelf: Showplace Cabinetry, walnut with Sparrow stain
Cabinetry supplied through: C. DePina Kitchens + Interiors
Countertop: Cambria Notting Hill
Plumbing fixtures: Kohler Tone collection, matte black
Vanity hardware: Top Knobs Tuscany collection, Tuscan Bronze
Floor tile: Bestile Roma Cream Vein
Shelf brackets: Signature Hardware Keeton cast iron shelf brackets
Wall paint: Benjamin Moore Kendall Charcoal HC-166